INSTALLATION
- Check the shop drawing is approved.
- Check the method statement is approved.
- Check the materials are approved.
- Check the material types & sizes are correct.
- Check the earthing and lightning protection system is free of foreign materials.
- Check the alignment of conductors are correct.
- Check the conductors are fixed properly with clips, straps and clamps.
- Check the clips/strap/clamp spacing is adequate.
- Check the jointing and welding points of conductors are fixed properly.
- Check the rods are installed at correct positions (to the coordinates provided by survey team).
- Check the test joints are accessible.
- Check the earthing jumpers installed as per project requirements.
- Check the earth bar cable jointing bolts are screwed properly.
- Check thermoweld connections are according to the specifications.
- Check all lugs are properly crimped and bolted.
- Check the vertical and horizontal position straightness of earthing & lightning protection installation.
FINAL CHECKS
- Check there are no missing/damaged parts in the installation.
- Check that there are no sharp edges/burrs on the installations.
- Test earth resistance by calibrated test device.
- Check continuity of the earthing cables.