- Check name plate, labelling, ID tags and warning signs correct to drawings / data sheets.
- Confirm no mechanical damage.
- Cable glands are the correct type and size as per cable schedule and installed according to specifications.
- Confirm location of local station against layout drawings and specification.
- Confirm properly supported.
- Confirm spare cable entries are correctly sealed.
- Check internals clean and moisture free.
- Check mechanical operation of push button & Auto / Manual controls.
- E-Stop lockable and protection against accidental operation as per specification.
- Confirm external cabling is undamaged.
- Confirm connection and termination tight.
- Earth bar and earthing correct, tight and continuity checked.
- Check gaskets and seals are installed and not damaged.
- Installation drawings have been “Red Lined” as per the Project Completions Procedure.