- Confirm the cable type is as per cable schedule and drawings.
- Confirm the cable identification and core markers are correct at each end, and at all transits (if applicable).
- Bending radius and stretch prevention is according to specification and the gland is not stressed by the cable.
- Cable glands are the correct type and size as per cable schedule and installed as per specification.
- Confirm gland earth bonding is correct to design specification.
- Ensure gland plates for single core cables are non-magnetic.
- Check terminations and earth connections are tight and correct.
- Ensure the correct size of crimp connector has been used.
- Confirm there is no visible damage and that the cable is mechanically protected, and supported as per installation specification.
- Cable suitably fastened according to specification.
- Confirm the spare cores and screens are made off correctly and earthed in accordance with the drawings and specification.
- Confirm cable routing and segregation is in accordance with the specification.
- Confirm cable screening (shielding) as per specification.
- For fieldbus cables record cable installed length. (__________m)
- Installation drawings have been “Red Lined” as per the project completions procedure.